Reporting
For UK Services and the Client to comply with TR19 Legislation and the Building Engineering Services ( B&ES ) Publication, it is compulsory to report on works carried out. The report is an essential part of both the Pre clean and Post clean.
​
The Report is to include the following;
​
-
WFTT ( Wet Film Thickness Tests ) are to be taken at key points within the system to establish contamination levels, photographic evidence of these tests should be taken and Micron reading recorded.
-
Photographic records of contamination levels at all key points must be taken before clean continues, these are repeated in the exact same points after clean.
-
Drawings of Extraction System
-
Additional works to be carried out i.e. new Access doors
-
Recommended Cleaning schedule
-
Problems i.e leakage and maintenance issues.
-
An Advisory note should it be required.
Key Areas where photographic evidence and WFTT readings must be taken;
​
-
Exhaust point of extraction system
-
Ductwork riser, every 3m or where access can be gained.
-
Silencers should they be required
-
Front of Fan
-
Back of Fan
-
Fan Housing
-
Canopy
-
Behind filters ( baffles )
-
Ductwork 1m from Canopy
-
Ductwork 3m from Canopy
-
Ductwork 5m from Canopy
-
Ductwork 10m from Canopy
-
Ductwork 20m from Canopy
​
Pre and Post report
​
Pre clean report
​
​
​